The downtown electrical upgrade is part of Nelson Hydro’s long range plan to upgrade the distribution system to 25 kV.

Working in 100 block of Hume Lane, underground conduits for primary and secondary electrical cable, along with conduits for City of Nelson fiber optic cable have been installed, encased in concrete.

Conduits will be installed so that secondary cables can be installed to feed the pole line from the new padmounted transformers.

The vaults are junction boxes that will be formed directly into the concrete sidewalk.

Baker Street was crossed one half at a time in order to maintain traffic flow along Baker Street.

For more information please call (250) 352-8240.

 